Oaklands Hill Wind Farm

Oaklands Hill Panoramic Photo

Timetable

December 2005

  • Wind monitoring began

February 2006

  • Planning consultants appointed

Quarter 4 2006 to Quarter 1 2007

  • Draft turbine layout identified
  • Equipment suppliers identified
  • Presentation to Southern Grampians Shire Council
  • Presentation to Ararat Rural City Council
  • Undertake detailed studies of:
    • Flora and fauna (spring and summer surveys for birds, bats and other fauna)
    • Noise
    • Indigenous factors
    • Heritage and tourism impact
    • Electromagnetic impact
    • Visual assessment
    • Geographical area

Quarter 2 to Quarter 3 2007

  • Consultation with direct neighbours and key stakeholders
  • Open day to receive and discuss all public submissions and address any concerns.
  • Lodge planning application with Minister for Planning. (Because the wind farm is over 30 MW the Minister is responsible for determining the application)

Quarter 4 to Quarter 1 2008

  • Planning Panel hearings

Quarter 3 2008

  • Planning approval expected

Quarter 1 2009

  • Design and construction of the wind farm commences