Skip to:
Main content
Sub navigation
Main navigation
Oaklands Hill Wind Farm
Main Navigation
Home
The Project
Project Overview
History
Site Location and Layout
Electrical Connection
Community Benefits
The Process
Planning Phase
The Process
Timetable
Consultation
Environment
Environment
Global Warming
Benefits of Wind
Newsroom
Press Releases
Current Status
Library
Library
FAQ
Facts
Links
Planning Permit
Employment
About Us
Contact Us
The Process
Planning Phase
The Process
Timetable
Consultation
Timetable
December 2005
Wind monitoring began
February 2006
Planning consultants appointed
Quarter 4 2006 to Quarter 1 2007
Draft turbine layout identified
Equipment suppliers identified
Presentation to Southern Grampians Shire Council
Presentation to Ararat Rural City Council
Undertake detailed studies of:
Flora and fauna (spring and summer surveys for birds, bats and other fauna)
Noise
Indigenous factors
Heritage and tourism impact
Electromagnetic impact
Visual assessment
Geographical area
Quarter 2 to Quarter 3 2007
Consultation with direct neighbours and key stakeholders
Open day to receive and discuss all public submissions and address any concerns.
Lodge planning application with Minister for Planning. (Because the wind farm is over 30 MW the Minister is responsible for determining the application)
Quarter 4 to Quarter 1 2008
Planning Panel hearings
Quarter 3 2008
Planning approval expected
Quarter 1 2009
Design and construction of the wind farm commences